Difference between revisions of "Plan Reviews and ProjectWise - PW2402"

From DelDOT CADD Wiki

(Created page with "<div class="noautonum cFloat">__TOC__</div> <p class="h2_outtoc">Introduction</p> <p> The following workflow shall be utilized when information contained within <b>ProjectW...")
 
Line 9: Line 9:
<p class="h2_outtoc">Placement of files: DelDOT Project Managers (Consultant Projects)</p>
<p class="h2_outtoc">Placement of files: DelDOT Project Managers (Consultant Projects)</p>
<div class="tab">
<div class="tab">
   <p>The <i>Consultant</i> shall place all necessary documents for review into the appropriate folder(s) under the consultant’s <b>800 - MILESTONE SUBMITTALS</b> folder structure in <b>ProjectWise</b>.</p>
   <p>The <i><b>Consultant</b></i> shall place all necessary documents for review into the appropriate folder(s) under the <b><i>Consultant’s</i></b> <b>800 - MILESTONE SUBMITTALS</b> folder structure in <b>ProjectWise</b>.</p>
   <p>The <i>DelDOT Project Manager</i> must copy these documents from the consultant side over to the DelDOT side. This is necessary as the internal review sections do not have access to the consultant side. <span class="tooltip"><span class="justthetip">!</span><span class="tooltiptext">As a reminder, the DelDOT PM has read access to the entirety of the Consultant work area so it is not necessary to use the 170_FILE_TRANSER folder.</span></span></p>
   <p>The <i>DelDOT Project Manager</i> must copy these documents from the <b><i>Consultant</i></b> side over to the <b><i>DelDOT</i></b> side. This is necessary as the <b>internal review sections do not have access to the <b>Consultant</b> side.</b> <span class="tooltip"><span class="justthetip">!</span><span class="tooltiptext">As a reminder, the DelDOT PM has read access to the entirety of the Consultant work area so it is not necessary to use the 170_FILE_TRANSER folder.</span></span></p>
   [[File:PW2402_01_001.png|link=|none]]
   [[File:PW2402_01_001.png|link=|none]]
</div>
</div>

Revision as of 09:13, 1 March 2024

Introduction

The following workflow shall be utilized when information contained within ProjectWise is to be distributed for review through Bluebeam.

Note: The ProjectWise folder structure and related contents can be found here. The 800_Milestone_SUBMITTALS subfolders are to be utilized for housing all submittal information.

Placement of files: DelDOT Project Managers (Consultant Projects)

The Consultant shall place all necessary documents for review into the appropriate folder(s) under the Consultant’s 800 - MILESTONE SUBMITTALS folder structure in ProjectWise.

The DelDOT Project Manager must copy these documents from the Consultant side over to the DelDOT side. This is necessary as the internal review sections do not have access to the Consultant side. !As a reminder, the DelDOT PM has read access to the entirety of the Consultant work area so it is not necessary to use the 170_FILE_TRANSER folder.

PW2402 01 001.png

Placement of files: Designers (In-House Projects)

Place all necessary documents for review into the appropriate subfolders under the DelDOT side 800 - MILESTONE SUBMITTALS folder structure in ProjectWise.

Bluebeam Submission process: DelDOT Project Managers and Designers (All Projects)

1. Fill out the appropriate Departmental Submission form on the DRC.

2. Provide a link to the appropriate submittal folder within ProjectWise.

To get this link, click on the appropriate folder and then right-click in the address bar located at the top and select Copy URL.

PW2402 01 002.png
This link will direct the support sections to where the supporting documentation is located within PW.

3. On the top section of the submission form, list all PDFs to be included in the Bluebeam submission.

PW2402 01 003.png
  • All files to be included must be explicitly listed out.
  • Only PDFs can be uploaded into Bluebeam.
  • If all files within a subfolder (e.g., 846_REPORTS) are to be included, you may list the folder instead and note that all files within the folder should be included.
  • Review the plan submission checklist to ensure all necessary files to be reviewed are listed.

Post-Review Process: DelDOT Project Managers and Designers (All Projects)

Once the session is closed and all comments have been responded to, place all documents back into ProjectWise under the appropriate folders.
Note: The plans containing the comment responses should be placed into the _PLANS folder. This is important as it allows reviewers to see the responses to their previous comments on subsequent reviews.
Important note: You should not extract the comments out of the PDF. Doing so breaks the link to the Plan location of the comment and leads to confusion.